1. Background:
The Mozambique Transmission Company – MOTRACO – is a limited liability company incorporated in Republic of Mozambique in 1998. The company is a joint venture of Electricidade de Moçambique (EDM), Eskom Holdings (Eskom), and Eswatini Electricity Company (EEC).
MOTRACO was created as a vehicle for co-operation with the primary objective of building, owning, and operating a smelter in Mozambique, and wheeling power to EEC and EDM.
View the RFP Document2. Scope of Work:
Item | Description | Quantity |
---|---|---|
1 | Auto-Ranging Voltage Indicator for 132kV, 275kV, and 400kV | 3 units |
3. Format of Proposal:
The proposal must be detailed and present the following:
- Cost of material;
- Material datasheet;
- Delivering cost at Marathon Substation;
- Any other applicable costs.
4. Address:
Marathon Substation
Situated +/- 11KM outside Nelspruit on R37 Lydenburg / Mashishing Road.
The first Eskom on the right-hand side.
Att: Relias Nokeri or Ampie Louw
5. Clarifications:
All clarifications shall be submitted by email to MOTRACO to the attention of:
- Name: Virgilio Laisse, Operations Engineer
- Email: Vlaisse@motraco.co.z
- Cc: esitoe@motraco.co.mz
6. Closing Date:
The proposals must be submitted no later than 03:00 PM o’clock on 23rd October 2024.